Week 7 (28 September 2015)

The new steel columns supporting the roof trusses have been installed awaiting the arrival of the roof trusses.

 

Removal of the existing concrete sill along the southern side has been finished with a small percentage remaining on the northern elevation.

 

Arrival of the roof trusses for the first 3 bays have arrived with the remaining trusses to arrive mid next week.

 

 