Gallery: Progress at week 6

Week 6 (21 September 2015)

Redesign of the fixing plate for the new steel columns was required, due to the varying tolerances in the location of the steel beams within the existing concrete slab.

 

70% of the nave sandstone has been ordered and is currently being worked offsite.

 

Removal of the existing concrete sill continued, in preparation for the new sandstone to continue up the wall to the underside of the eave.

 

Several days of wet weather hampered progress on the upper level.

 

 