Gallery: Progress at week 57

Week 57 (12 September 2016)

 

Further replacement of stone around the base of the tower is ongoing and will do so for the coming weeks.

 

The render for the new toilet amenities has been applied and is now ready for painting.

 

Waterproofing has been has been applied to the toilet amenities in preparation for tiling to occur next week.

 

The levee bank stair case walls have the applied finish, with the steps currently being formed up ready for concrete.

 

Set-out and establishment of pathways around the chapel is still ongoing. The proposed steps to the chapel/bell tower forecourt is in the process of being formed up ready for concrete.

 

The proposed landscape lighting is in the process of being installed.

 