Gallery: Progress at week 56

Week 56 (5 September 2016)

 

The removal of the scaffolding around the bell tower has now been completed.

 

Further replacement of stone around the base of the tower is ongoing and will do so for the coming weeks.

 

The new toilet amenities roof, gutters and downpipes have been installed. The external brickwork also has been completed this week awaiting render to be applied.

 

Waterproofing and tiling to commence next week within the toilet amenities.

 

The levee bank stair case is currently having a render applied to the walls prior to a stone capping being installed which will follow the profile of the walls.

 

Setout and establishment of pathways around the chapel to commence next week.

 