Gallery: Progress at week 45

Week 45 (20 June 2016)

 

The large gothic window which fronts Cathedral Street, has been removed for closer examination. Any deteriorated timbers will be replaced to match existing.

 

The renderer will is now on site to commence the rendering of the Northern and Southern nave walls.

 

The decorative stone around the bell tower parapet continues to be laid and anchored, as part of the structural improvements.

 