Gallery: Progress at week 43

Week 43 (6 June 2016)

 

Stone repair works around the eight bell tower/louvre windows are now complete and awaiting the install of the lourved windows.

 

JJJ course above the tower cornice has been delivered and installed as of 20/5/16.

 

Injected Westox damp proof course to the north and south nave is complete.

 

Cocoon poultice to the North and South nave was completed 14/5/16.

 

Renderer will be on site in four weeks time to commence the rendering of the North and South nave walls.

 

The copings to the North West and South West gables are currently being cut and fitted.

 

Pointing works to the tower are now approximately 75% complete.

 