Gallery: Progress at week 10

Week 10 (19 October 2015)

 

The eastern gable end is now in readiness for the cedar cladding to be installed.

 

The steel work for the strengthening of the Bell Tower has now been installed with the steel rods now chemically anchored into the sandstone walls.

 

The Bell Tower scaffolding has now been completed and certified (minor delays due to wet weather).

 

The removal of the pinnacles from the tower and nave have been delayed (due to delays with the certification of the scaffolding) and rescheduled for next week.

 

New sandstone continues to be worked off site and will start to be brought to site now that the scaffold and roof trusses have been installed.

 